|
For most of the last century coal mining dominated Whitburn's industry.
At it's peak the central belt of Scotland was littered with hundred
of mines employing thousands of workers. However, by the end of the
century Scotland only had one deep mine left and it wasn't in Whitburn.
The 1984/85 industrial dispute between the National Coal Board (NCB)
and the National Union of Mineworkers (NUM) decimated the mining industry
and Polkemmet Colliery was a major casualty. At that time it was the
second largest employer in West Lothian behind the large British Leyland
truck factory in Bathgate. Although nearly 1400 people worked at the
pit, only around 13% actually lived in Whitburn. The rest came from
other towns and villages mainly within a thirty mile radius of Polkemmet.
While 13% is a fairly low amount the loss of the mine undoubtedly
delivered a severe blow to the towns economy.
Sinking began on No.1 shaft in 1913 and No.2 three
years later. Work was stopped in 1917 until the end of the First World
War in 1918. The shafts reached the coal in 1921 and production started
in 1922. Following nationalisation just after the end of the Second
World War the rate of development speeded up and additional manpower
recruited until by 1952 output had increased to appox. 2000 tons daily.
This increase in output during the 1st five years of nationalisation
was obtained without carrying out any major re-construction. However,
considerable effort was required to increase steaming and power generating
capacity and to develop new face room. Compared with modern standards,
the surface handling arrangements were obsolete and the winding, steam
raising and power plant rather inefficient. The winding engines were
in poor condition and had, in fact, in recent years required extensive
repairs. It was originally intended to electrify the colliery by bringing
in electrical power from the South of Scotland Electricity Board,
but due to the urgency for coal production due to the war effort and
the long time it would have taken to bring in power, the intention
was never realised. An interim scheme for extending boiler and generating
capacity was carried out with utmost despatch and considerable success
during 1949. Since no further increase in output or efficiency could
be obtained with the existing equipment, it was decided in 1952 that
the time was right for carrying out complete electrification &
re-construction.
Polkemmet
was a self-contained unit using orthodox steam winders and having
a generating station for electric power. Shaft pumping was also carried
out using steam power. The purpose of the re-organisation of the colliery
was to raise the daily saleable output from 2000 to 3000 tons. This
increase in output was designed to meet the increasing demand for
coking coals, which has a low sulphur content and minimal phosphorous
contamination which made it suitable for steel making plants. Approximately
95% of Polkemmet coal was sold to the British Steel works at Ravenscraig
with the remainder sold for domestic use. To deal with this additional
output, the re-organisation envisaged, except for space heating, the
complete electrification of the colliery, including the installation
of new electric winders and ventilating fan. Re-organisation in 1958
increased capacity to 4000 tons daily. More recent investment was
relatively limited until 1979/80 when just over £326,000 was spent.
Capital expenditure rose to just under £1million in 1981/82 most of
which was on the construction of long term underground roadways.
The "Report of the Public Inquiry into the proposed
closure of Polkemmet Colliery, August 1985" showed that in 1982/83,
the latest year unaffected by major disputes, investment per man in
the NCB (only those at collieries) as a whole was £3651 but in the
Scottish area alone it was down to £2182. The report also showed that
the Scottish Area since 1974/75 received not only the lowest absolute
amount of all NCB areas for capital expenditure, but also a significantly
lower amount per man. Polkemmet Colliery faired even worse in receiving
even less investment per man than the average in the Scottish area.
the below average level investment in Polkemmet Colliery was a significant
contributor to it's continued loss making. The NCB's internal accounts
suggested that in the first six months of the financial year 1983/84
the colliery was losing £8.03 per tonne.
During the 1984/85 industrial dispute pumping stopped
and flooding damaged the pit. After the dispute pumping started up
again and although the unions argued that the colliery could be
recovered in April 1985, the NCB announced it's intentions to close
the colliery which followed soon after. Pumping finally ceased in
1986. This was not the end of the story. Monitoring in the area alerted
the Scottish Environment Protection Agency (SEPA) and the Coal Authority
that rising mine
waters were a major cause for concern. SEPA targeted the problem as
their priority site for action in Scotland. The feasibility study
commissioned by the Coal Authority suggested that mine water contaminated
with iron could break out along coal outcrops towards the end of the
90s causing potential pollution to the River Almond which flows alongside
Whitburn and through Polkemmet Country Park. West Lothian Council
and SEPA came up with a scheme to pump from the Polkemmet shafts,
chemically treat the water and discharge it into the Cultrig Burn.
The construction works commenced in January 1998 and were completed
two months later. Early results looked good in that the mine waters
were soon under control but work continues to establish a long term
solution to the problem.
The vacated area of the colliery and surrounding land
is getting a new lease of life the Polemmet OCCS / Heartlands scheme. This ambitious £500 million regeneration plan will change
the landscape of Whitburn forever with championship size golf courses,
high tech. business park, hotel and leisure facilities.
|